Mechanical and electrical assembly works of the PASTA CORTA machine, Beira - MZ plant.
Running from May 2023 to October 2023.
Last updated 05/12/2025
Piping works related to the pasta machine, steam piping, vacuum piping, cold piping, air piping, etc.
Performances starting from June 2023 to October 2023.
Last updated 05/12/2025
#1-Mechanical and electrical assembly works for the construction of a new loading system for the Milling site and connection, with conveyor belts, to the existing silos. Performances starting from March to October 2024.
#2-Mechanical assembly works for the construction of support structures for the grain containment silos being processed in the new Milling line. Performances starting from July to November 2024.
Last updated 05/12/2025